Description

As part of ongoing investment in the North Sea by SSE Renewables and TotalEnergies, the Seagreen project is progressing to a stage where the offshore turbines are being installed and commissioned. However due to unforseen circumstances, the Offshore platfrom along with the offshore network hub is running behind schedule.

Working hand in hand with Vissim, SSE Renewables and Vestas Wind Energy to create a temporary network for command and control of the installed offshore wind turbines until the Offshore Platform is fully installed and commissioned to allow for safe access for commissioning engineers to the installed turbines.